Grounded Electrical Construction performed the Genertor Replace project at the Maryland Highway Administrations District 3 Facility in Greenbelt, MD as a prime contractor. We replaced the existing generator with a new 350KW natural gas generator, 600A & 100A ATS's and new gear, all while the facility was occupied and operational. In addition to new equipment, we relocated existing loads to the new ATS's to ensure they had emergency back-up power in the event of a utility power outage.
Maryland State Highway Administration - District 3 Generator Replacement
date:
7/21/2017
subjects:
Maryland State Highway Administration - District 3 Generator Replacement
Location: Greenbelt, MD
- Owner: State of Maryland Department of Transportation State Highway Administration
- Electrical Engineer: Johnson, Mirmiran & Thompson
- General Contractor: Grounded Electrical Construction